Incomplete capital works

Expected year of completion 

2026-27

Estimated total cost 2025-26 ($’000) 

5,552

Estimated remaining cost to complete ($’000)

1,192 

Total cost variation 2024-25 to 2025-26 ($’000)

Estimated total cost reported in 2024-25 ($’000) 

5,552 

Explanation for variance ( ≥ 10%)

Expected year of completion 

2026-27

Estimated total cost 2025-26 ($’000) 

9,632

Estimated remaining cost to complete ($’000)

381 

Total cost variation 2024-25 to 2025-26 ($’000)

Estimated total cost reported in 2024-25 ($’000) 

9,632

Explanation for variance ( ≥ 10%)

Expected year of completion 

2026-27

Estimated total cost 2025-26 ($’000) 

5,000

Estimated remaining cost to complete ($’000)

438 

Total cost variation 2024-25 to 2025-26 ($’000)

Estimated total cost reported in 2024-25 ($’000) 

5,000

Explanation for variance ( ≥ 10%)

Expected year of completion 

2026-27

Estimated total cost 2025-26 ($’000) 

1,500

Estimated remaining cost to complete ($’000)

762 

Total cost variation 2024-25 to 2025-26 ($’000)

Estimated total cost reported in 2024-25 ($’000) 

1,500

Explanation for variance ( ≥ 10%)

Expected year of completion 

2026-27

Estimated total cost 2025-26 ($’000) 

3,595

Estimated remaining cost to complete ($’000)

40 

Total cost variation 2024-25 to 2025-26 ($’000)

767 

Estimated total cost reported in 2024-25 ($’000) 

2,828

Explanation for variance ( ≥ 10%)

Approved injection of additional capital funding.

Expected year of completion 

2026-27

Estimated total cost 2025-26 ($’000) 

81,059

Estimated remaining cost to complete ($’000)

79,648 

Total cost variation 2024-25 to 2025-26 ($’000)

Estimated total cost reported in 2024-25 ($’000) 

81,059

Explanation for variance ( ≥ 10%)

Expected year of completion 

2027-28

Estimated total cost 2025-26 ($’000) 

6,519

Estimated remaining cost to complete ($’000)

6,131

Total cost variation 2024-25 to 2025-26 ($’000)

n/a

Estimated total cost reported in 2024-25 ($’000) 

n/a

Explanation for variance ( ≥ 10%)

Expected year of completion 

2027-28

Estimated total cost 2025-26 ($’000) 

7,000

Estimated remaining cost to complete ($’000)

391

Total cost variation 2024-25 to 2025-26 ($’000)

0

Estimated total cost reported in 2024-25 ($’000) 

7,000

Explanation for variance ( ≥ 10%)

Expected year of completion 

2027-28

Estimated total cost 2025-26 ($’000) 

22,893

Estimated remaining cost to complete ($’000)

1,570

Total cost variation 2024-25 to 2025-26 ($’000)

0

Estimated total cost reported in 2024-25 ($’000) 

22,893

Explanation for variance ( ≥ 10%)

Expected year of completion 

2027-28

Estimated total cost 2025-26 ($’000) 

7,947

Estimated remaining cost to complete ($’000)

7,771

Total cost variation 2024-25 to 2025-26 ($’000)

n/a

Estimated total cost reported in 2024-25 ($’000) 

n/a

Explanation for variance ( ≥ 10%)

Expected year of completion 

2028-29

Estimated total cost 2025-26 ($’000) 

42,150

Estimated remaining cost to complete ($’000)

31,628

Total cost variation 2024-25 to 2025-26 ($’000)

0

Estimated total cost reported in 2024-25 ($’000) 

42,150

Explanation for variance ( ≥ 10%)

Expected year of completion 

2028-29

Estimated total cost 2025-26 ($’000) 

9,963

Estimated remaining cost to complete ($’000)

3,767

Total cost variation 2024-25 to 2025-26 ($’000)

0

Estimated total cost reported in 2024-25 ($’000) 

9,963

Explanation for variance ( ≥ 10%)

Expected year of completion 

2028-29

Estimated total cost 2025-26 ($’000) 

21,135

Estimated remaining cost to complete ($’000)

18,591

Total cost variation 2024-25 to 2025-26 ($’000)

5,369

Estimated total cost reported in 2024-25 ($’000) 

15,766

Explanation for variance ( ≥ 10%)

Approved injection of additional capital funding.

Expected year of completion 

2028-29

Estimated total cost 2025-26 ($’000) 

67,114

Estimated remaining cost to complete ($’000)

58,992

Total cost variation 2024-25 to 2025-26 ($’000)

10,474

Estimated total cost reported in 2024-25 ($’000) 

56,640

Explanation for variance ( ≥ 10%)

Approved injection of additional capital funding.

Expected year of completion 

2029-30

Estimated total cost 2025-26 ($’000) 

167,002

Estimated remaining cost to complete ($’000)

160,887

Total cost variation 2024-25 to 2025-26 ($’000)

0

Estimated total cost reported in 2024-25 ($’000) 

167,002

Explanation for variance ( ≥ 10%)

Expected year of completion 

To be determined

Estimated total cost 2025-26 ($’000) 

Estimated remaining cost to complete ($’000)

Total cost variation 2024-25 to 2025-26 ($’000)

Estimated total cost reported in 2024-25 ($’000) 

6,021

Explanation for variance ( ≥ 10%)

This is being held over until commencement of the expansion of the St John of God Midland Public Hospital Emergency Department.

Complete capital works

Estimated total cost in 2024-25 ($’000)

28,254 

Total cost variation 2024-25 to 2025-26 ($’000)

-400

Total cost to complete in 2025-26 ($’000)

27,854

Explanation for variation ( ≥ 10%)

Estimated total cost in 2024-25 ($’000)

1,843 

Total cost variation 2024-25 to 2025-26 ($’000)

-175

Total cost to complete in 2025-26 ($’000)

1,668

Explanation for variation ( ≥ 10%)

Estimated total cost in 2024-25 ($’000)

7,000 

Total cost variation 2024-25 to 2025-26 ($’000)

0

Total cost to complete in 2025-26 ($’000)

7,000

Explanation for variation ( ≥ 10%)

Estimated total cost in 2024-25 ($’000)

881 

Total cost variation 2024-25 to 2025-26 ($’000)

0

Total cost to complete in 2025-26 ($’000)

881

Explanation for variation ( ≥ 10%)

Estimated total cost in 2024-25 ($’000)

3,000

Total cost variation 2024-25 to 2025-26 ($’000)

0

Total cost to complete in 2025-26 ($’000)

3,000

Explanation for variation ( ≥ 10%)

Estimated total cost in 2024-25 ($’000)

3,000 

Total cost variation 2024-25 to 2025-26 ($’000)

-2,510

Total cost to complete in 2025-26 ($’000)

490

Explanation for variation ( ≥ 10%)

Lower than anticipated site and facility audits as they were funded as part of separate project.

Estimated total cost in 2024-25 ($’000)

14,545

Total cost variation 2024-25 to 2025-26 ($’000)

700

Total cost to complete in 2025-26 ($’000)

15,245

Explanation for variation ( ≥ 10%)

The Department of Health approved $700,000 in funding to support dual processing activities associated with project implementation.

Estimated total cost in 2024-25 ($’000)

3,898 

Total cost variation 2024-25 to 2025-26 ($’000)

0

Total cost to complete in 2025-26 ($’000)

3,898

Explanation for variation ( ≥ 10%)

Notes:

  1. The above information is based upon the:
    i. 2024–25 EMHS published Annual Report
    ii. 2026−27 published State Budget Papers and 2025-26 Service Agreement for EMHS.
  2. Completion timeframes are based upon a combination of the approved delivery schedule, scope and budget at the time of reporting, and reflect the financial completion of the project.
  3. Only capital projects that were administered by EMHS are reflected in the table.
  4. Incomplete capital works is defined to be financially incomplete projects, and Completed is defined to be financially completed or fully expended projects.
  5. Estimated total cost of project and Estimated remaining cost to complete are reflected as per the 2026-27 Service Agreement and are subject to changes following outcomes of future Mid-Year review and budget process.
  6. Variance represents the difference between the estimated total cost of the project in the 2026-27 published Budget Papers in comparison to the total cost or estimated total cost of the project as reported in the 2024–25 EMHS Annual Report. An explanation is provided where a variance is greater than or equal to 10 per cent. 
(L-R) Ben Noteboom, Joel Gurr, Sally Carbon OAM, Minister Meredith Hammat, Zaneta Mascarenhas, Minister John Carey and Chandima Hiyare-Hewage.

Industrial relations

EMHS engaged with the WA Health System in contributing to negotiations for new Industrial Agreements for 2025-26 including:

  • WA Health System Engineering and Building Services Industrial Agreement 2025 
  • WA Health System – Medical Practitioners (Clinical Academics) AMA Industrial Agreement 2026.

EMHS is now implementing new and modified conditions of employment contained in these Industrial Agreements, including implementation of improved career pathways for allied health professionals and anaesthetic technicians.  

EMHS continued with its commitment to a permanent workforce and to reducing its reliance on agency workers and a casual workforce.